Reconciliation Of Owner And Contractor Views In Heavy Construction Projects
Keywords
Change orders; Claims; Construction management; Contractors; Legal factors; Owners; Productivity
Abstract
Delay and loss of productivity are the two main types of damage experienced by the contractor when the owner issues a change order. Courts have recognized critical path method schedule analysis as the preferred method of identifying and quantifying critical delays. As for the inefficiency damages, there is no direct way of measuring inefficiency due to its qualitative nature and the difficulty of linking the cause of the productivity loss to the damage. Most of the scholarly work published in this area was based on data supplied by the contractors; and that explains why there are discrepancies between what the contractor asks for and what the owner believes the contractor is entitled to. This study addresses the need for a statistical model to quantify the productivity loss from verifiable site data such as owner's daily reports, change orders, drawings, and specifications, rather than rely solely on contractor surveys. A model is developed and validated to quantify the productivity loss in pipe work in roadway projects due to the change orders. The productivity loss study analyzed two sets of data that include: (1) variables that predict which of the two parties, the owner and the contractor, contributed to the productivity loss; and (2) variables that predict, from the legal viewpoint, productivity losses which only the owner is responsible for. The study showed the difference between what the contractor asked for and what he/she is actually entitled to. This model can be used by both the owner and the contractor to quantify the productivity loss due to change orders, and to offer an objective approach to reconcile their differences. This study concludes with an example to demonstrate the use of the model. © 2008 ASCE.
Publication Date
1-1-2008
Publication Title
Journal of Professional Issues in Engineering Education and Practice
Volume
134
Issue
1
Number of Pages
-
Document Type
Article
Personal Identifier
scopus
DOI Link
https://doi.org/10.1061/(ASCE)1052-3928(2008)134:1(128)
Copyright Status
Unknown
Socpus ID
37249035928 (Scopus)
Source API URL
https://api.elsevier.com/content/abstract/scopus_id/37249035928
STARS Citation
Serag, Engy; Oloufa, Amr; and Malone, Linda, "Reconciliation Of Owner And Contractor Views In Heavy Construction Projects" (2008). Scopus Export 2000s. 11006.
https://stars.library.ucf.edu/scopus2000/11006